executing two designer programs sequentialy
terry terry
ggjos@hotmail.com
Tue, 01 Jun 2004 20:55:53 +0000
Hi,
I have 2 designer procedures named 88 and 89 in Qdesign. After 88 runs
and updates the screen the new data is used in calculations for the 89
procedure. However when run separately as in 88 then 89 every thing goes
well. But when I enter 88/89 in the action field in the screen , 89 does not
run because the updated data from 88 does not stay unless the screen is
refreshed and the info is called up fresh. I tried “push update” in the
procedure but to no avail. Help Thanks.
E.g.:
Procedure designer 88
Begin
push update
Qtp Auto=1
Qtp Auto=2
Qtp Auto=3 ;inputs date-to-start in screen
Push update
End
Procedure designer 89
begin
Qtp Auto=1 ; needs date-to-start to continue
Qtp Auto=2
Qtp Auto=3
end